All northbound lanes of Interstate 205 will close Nov. 20-23 for a major stage of the Abernethy Bridge project.

Crews will slide the northbound bridge section about eight feet outward onto new earthquake-resilient piers, according to ODOT.

The closure begins at 10 p.m. Friday, Nov. 20, and northbound lanes are scheduled to reopen by 5 a.m. Monday, Nov. 23. Southbound I-205 lanes and ramps will stay open.

Three northbound on-ramps will also shut down during the closure: OR 43, 10th Street and Stafford Road. The Stafford Road closure hits Tualatin-area commuters heading north especially hard.

ODOT's signed regional detour sends northbound traffic onto I-5 and I-84 to bypass the closed stretch between OR 43 and OR 99E. Local traffic can use the Arch Bridge to cross the Willamette River.

How the slide works

Workers will be on-site around the clock from Friday night through early Monday. ODOT said crews will first use hydraulic jacks to lift the upper bridge structure about two inches off its existing supports. Additional jacks will then push the bridge sideways at about four inches every 15 minutes until it reaches the eight-foot mark.

The slide is how ODOT is widening the main span, creating space for an additional 16 feet of roadway in the middle of the interstate crossing over the Willamette River between Oregon City and West Linn. The southbound side of the bridge will be slid in the other direction during a separate weekend later in 2026, ODOT said.

After the slide, crews will inspect the structure, reconnect joints, lighting and lane striping before reopening to traffic.

Weather could change plans

ODOT said the work could be postponed if strong winds appear in the forecast. Drivers can check conditions at TripCheck.com before traveling.

The broader Abernethy Bridge upgrade, led by ODOT media contact David House's team, is expected to finish in 2027. It includes seismic improvements, ramp realignments and new bicycle and pedestrian routes.