Engineers moved a 1,030-foot section of the Abernethy Bridge on Interstate 205 nearly eight feet sideways over the weekend, part of a project to widen the bridge and strengthen it against major earthquakes.
The bridge spans the Willamette River between Oregon City and West Linn. The northbound section weighs about 18,120,000 pounds, according to the Oregon Department of Transportation.
Crews used hydraulic jacks to lift the section about two inches off its supports, then pushed it sideways about four inches every 15 minutes.
"We picked it up about two inches, and then we moved it over about seven and a half feet, and then we put it back down on its supports," project Resident Engineer Ian Cannon said.
The slide began late Friday night, Nov. 20, and took about six hours, continuing into early Saturday morning. Crews worked around the clock over the weekend to move the northbound section onto newly widened, earthquake-resilient piers.
After the move, crews inspected the structure, reconnected it to the roadways at each end, restored lighting connections and guardrail, and restriped the lanes before reopening the bridge to traffic.
"We moved it an inch at a time to make sure we were keeping it straight and not over-stressing the bridge, and once we got it where we wanted it, we lowered it down again," Cannon said. "The lifting and moving of a very large bridge is very unusual just because of the magnitude of it."
Drivers will notice that the lanes have shifted, but ODOT said crossing the bridge will feel much the same as before.
The southbound section will undergo a similar move during another weekend later this year, shifting about eight feet in the opposite direction. When both moves are complete, the two sides of the bridge will be 16 feet farther apart, creating room for future construction in the center.
The bridge slide is part of a larger project to make the Abernethy Bridge the first interstate highway bridge over the Willamette River in the Portland metro area able to withstand a major earthquake. The project also includes realigning nearby OR 99E on- and off-ramps and building new bicycle and pedestrian routes, sidewalks and safer crossings in West Linn and Oregon City, according to ODOT's project overview.
Bridge construction is expected to finish sometime in 2027. Residents can sign up for project updates through ODOT's Abernethy Bridge project website.